Increased workload at the wastewater treatment plant

20 January 2025

Officially launched on November 4, renovation and modernization work on Haliotis2 is gradually ramping up at the start of this year. On January 06, 2025, work began on the foundations of the future offshore pumping station at 2 shifts, over an initial working day from 6 a.m. to 10 p.m.. This marks the start of construction of the first building of the future wastewater treatment plant, after the land on which it will be built had been prepared by earthworks since last November.